AEP/ENEL Mato Switching Station – Sentinel, OK – Completed July 2022
153 Turnkey Drilled Shafts 24” – 60” in diameter
The AEP Mato Switching station consisted of 153 drilled shaft foundations ranging from 24” to 66” of varying depths, along with various pad & slab foundations. Vantage also performed the layout of all foundations. Vantage utilized two drill rigs to complete the project on time.
Brazos River Electric Coop – Bosque Substation
GC:  Integrated Power Company

Location: Waco, TX
Construction Type:  Greenfield (New construction)
Scope: Drilled Pier Equipment Foundations, Slab/Pad Construction, Oil Containment Pit, and Transformer Pedestal
CV: $550k